BACKGROUND
The Horka Dam built in 1985 had water leakage problems in the maintenance tunnels well below grade. The maintenance tunnels required waterproofing for 1550 m2 of existing concrete.

SOLUTION
Krystol™ T1 and T2 were used on existing below grade concrete. Since the Krystol™ application in 1997 no leaks or wet spots have been observed.

Location West Czech Region, Czech Republic
Distributor Fosroc Veritech, Prague, Czech Republic
Applicator Realcrete, s.r.o.
Engineer Vltava River Administration, Inc.