Watch our webinar: Advanced Strategies for Integral Waterproofing Concrete in Modern Building Envelopes - Watch Now
21 Oct 2010
As a result of Vancouver’s Gateway Transportation Project and new Golden Ears Bridge, Pitt Meadows is quickly becoming a vital hub for the Fraser Valley and Vancouver.
Right in the centre of it all is the new urban living development - Meadows Gate Village Complex. At the heart of the new community are the Solaris Meadows Gate residential homes featuring 3 towers and 1 low rise. The steel and concrete structures feature modern conveniences and were designed using LEED building principles.
Pitt Meadows’ high water table was of concern for the builder. If water penetrated the concrete it could cause a breakdown in the rebar and threaten the long term durability of the buildings.
3500 cubic meters (4578 cubic yards) of Krystol Internal Membrane (KIM) treated concrete was used to waterproof all base slabs, all below grade exterior foundation walls as well as in the parking structure for the city library in the development.The Krystol Internal Membrane admixture was the perfect choice for the developer wanting to build using LEED principles. Krystol Internal Membrane:• Contains Zero VOCs (Volatile Organic Compounds)• Eliminates the need for tar or petroleum based materials• Greatly decreases jobsite wasteThe team also benefited from Krystol Internal Membrane’s ability to protect the reinforcing steel by preventing the penetration of water and waterborne contaminants that can cause corrosion to the reinforcing steel. Krystol Internal Membrane provided the Solaris development team the permanent waterproofing solution they were looking for.